ANDRITZ to modernize biomass boiler in Germany for more flexible fuel use
In Austria, ANDRITZ said it has received an order for the modernization of the biomass boiler at the combined heat and power plant Herbrechtingen in southern Germany.
The modernization will prepare the 49 MW bubbling fluidized bed boiler for operation with a broader range of fuels.
ANDRITZ said it will engineer, supply, and install a new open-grid nozzle floor, including the associated dismantling and pressure-part modifications. The upgrade will improve bed ash removal and support the boiler’s future operation with a broader range of fuels.
“With these modifications, we are strengthening the reliability of our plant while laying the foundation for more flexible plant operation,” said Jürgen Wiedenmann, Managing Director of Biomasse-Heizkraftwerk Herbrechtingen.