Vattenfall, CIP Dutch offshore wind farm delayed to 2032

August 14, 2025 |

In the Netherlands, offshoreWind.biz reported that the completion date for Vattenfall and Copenhagen Infrastructure Partners’ offshore wind farm at the IJmuiden Ver Beta site in the Netherlands has been pushed from late 2029 to 2032 due to the delayed completion of the Delta Rhine Corridor (DRC).

Vattenfall and CIP revealed the plans for the project, which will comprise a 2 GW offshore wind farm and a 50 MW floating offshore solar farm as well as a 1 GW electrolyser plant, in June 2024.

The Zeevonk joint venture has indicated that it is no longer financially and economically feasible to realize the project in line with the current permit due to the delayed completion of DRC. Through the DRC, green hydrogen produced at Maasvlakte could be transported to customers in the Netherlands, Belgium, and Germany, according to the report.

More on the story.