Permanent upgrades at 75-MW Tokushima-Tsuda biomass power plant completed

December 30, 2024 |

In Japan, RENOVA has completed installment of permanent improvements at the 75-MW Tokushima-Tsuda Biomass Power Plant and resumed regular operation on December 22, which has demonstrated continuing stable operations. The plant was shut down in December to undergo the improvement works following earlier maintenance work in April and July that also required shutdowns. The impact on the financial results for the fiscal year ending March 31, 2025 is already reflected in the forecast released on May 8, 2024.