Delorean confirms financial close on $43M Australian bioenergy facility

November 9, 2026 |

In Australia, Delorean’s Board has confirmed Financial Close on the 100% owned NSW1 Horsley Park Bioenergy Facility, co-located with Brickworks’ operations in Horsley Park, New South Wales.

The project can now move immediately into the procurement phase with construction then expected to commence on site in early 2027. The 25-year renewable gas supply agreement with Building Products Pty Limited and lease with The Austral Brick Co Pty Ltd (both wholly owned subsidiaries of Brickworks Limited) and the A$30.5m of grants are now active.

Firm commitments totaling A$1.4 million have been received for a private share placement.

The A$62.1 million gross project cost will be funded by;

– A$20.0 million grant from the NSW government

– A$10.5 million grant from the Australian Renewable Energy Agency (ARENA)

– A$20.0 million from Westpac

– A$1.6 million from funds already applied to project capital costs

– $A8.7 million from; a new Tanarra Facility D / R&D tax refunds / future DEL cash on hand

– A$1.3 million from private share placement

Tags: , ,

Category: Fuels

Thank you for visting the Digest.

}